Paraguay’s ANDE Plans 2027 End Date for Crypto Miners’ Special Power Contracts

As reported on November 14, 2026, Paraguay’s national electricity company, ANDE, planned to have all special power contracts for crypto miners expire on December 31, 2027. The plan was reported amid growing domestic electricity demand and competition from AI companies for low-cost hydropower. It was not described as an enacted rule.

ANDE expected to receive $350 million from crypto miners in 2026. As of April, miners had contracted for approximately 944 megawatts of power.

ANDE engineers had also proposed a 700-megawatt combined limit for mining, AI and data centers from 2028, with electricity allocated through bidding. That proposal had not been adopted.

Separately, Kuntur, a company associated with the Iguazú AI City project, had signed a 15-year supply contract with ANDE for up to 286 megawatts.